North Dakota power grid

North Dakota's operating portfolio is led by Wind, followed by Coal. Its 64 plants represent 10,162 MW of nameplate capacity. The dataset also reports 2,867 MW of proposed capacity.

Final 2024 state totalsPreliminary 2025 facilitiesCommunity-reported data centers
Operating capacity10,162 MWFinal EIA-860 2024
Power plants64101 operating generators
Proposed capacity2,867 MW28.2% of current capacity
Community-mapped locations1Incomplete OpenStreetMap coverage

Coverage quality

What is complete here?

PassState totalsFinal 2024 EIA-860 generator records cover the state.
PassFacility list2025 Early Release records are nationwide but preliminary.
LimitedData centersCommunity mapping is useful for discovery, not a complete inventory.

Generation portfolio

North Dakota capacity by fuel

Nameplate capacity · MW
Wind44.6%4,529 MW
Coal39.6%4,023 MW
Oil & gas10%1,012 MW
Hydro5.7%583 MW
Biomass0.1%10 MW
Industrial & other0.1%5 MW

Facility intelligence

Largest North Dakota power plants

EIA-860 2025 early release facility records
PlantPrimary fuelLocationUtilityOperating capacity
Coal CreekPlant 6030CoalUnderwood, NDMcLean CountyRainbow Energy Center1,216 MW
Antelope ValleyPlant 6469CoalBeulah, NDMercer CountyBasin Electric Power Coop954 MW
Pioneer Generation StationPlant 57881Oil & gasWilliston, NDWilliams CountyBasin Electric Power Coop897 MW
Milton R YoungPlant 2823CoalCenter, NDOliver CountyMinnkota Power Coop, Inc734 MW
Leland OldsPlant 2817CoalStanton, NDMercer CountyBasin Electric Power Coop656 MW
GarrisonPlant 2815HydroRiverside, NDMercer CountyUSACE-Omaha583 MW
CoyotePlant 8222CoalBeulah, NDMercer CountyOtter Tail Power Co450 MW
Lonesome Creek StationPlant 57943Oil & gasAlexander, NDMcKenzie CountyBasin Electric Power Coop363 MW
Aurora Wind ProjectPlant 63258WindTioga, NDWilliams CountyAurora Wind Project, LLC299 MW
Bison 4 Wind Energy CenterPlant 58872WindNew Salem, NDMorton CountyALLETE, Inc.205 MW

Methodology

Transparent by design

State totals and fuel mix use finalized EIA-860 2024 generator data. The facility table uses the EIA-860 2025 Early Release and is preliminary. Data-center counts use OpenStreetMap community records and measure mapped coverage, not the full market.