IA · State grid profile

Iowa power grid

Iowa's operating portfolio is led by Wind, followed by Coal. Its 306 plants represent 24,421 MW of nameplate capacity. The dataset also reports 633 MW of proposed capacity.

Final 2024 state totalsPreliminary 2025 facilitiesCommunity-reported data centers
Operating capacity24,421 MWFinal EIA-860 2024
Power plants306717 operating generators
Proposed capacity633 MW2.6% of current capacity
Community-mapped locations9Incomplete OpenStreetMap coverage

Coverage quality

What is complete here?

PassState totalsFinal 2024 EIA-860 generator records cover the state.
PassFacility list2025 Early Release records are nationwide but preliminary.
LimitedData centersCommunity mapping is useful for discovery, not a complete inventory.

Generation portfolio

Iowa capacity by fuel

Nameplate capacity · MW
Wind53.3%13,016 MW
Coal21.6%5,277 MW
Oil & gas21.4%5,236 MW
Solar2.8%678 MW
Hydro0.8%184 MW
Biomass0.1%21 MW
Storage0%11 MW

Facility intelligence

Largest Iowa power plants

EIA-860 2025 early release facility records
PlantPrimary fuelLocationUtilityOperating capacity
Walter Scott Jr Energy CenterPlant 1082CoalCouncil Bluffs, IAPottawattamie CountyMidAmerican Energy Co1,648 MW
LouisaPlant 6664CoalMuscatine, IALouisa CountyMidAmerican Energy Co812 MW
OttumwaPlant 6254CoalOttumwa, IAWapello CountyInterstate Power and Light Co726 MW
Marshalltown Generating StationPlant 58236Oil & gasMarshalltown, IAMarshall CountyInterstate Power and Light Co709 MW
George Neal SouthPlant 7343CoalSalix, IAWoodbury CountyMidAmerican Energy Co696 MW
Emery StationPlant 8031Oil & gasClear Lake, IACerro Gordo CountyInterstate Power and Light Co603 MW
George Neal NorthPlant 1091CoalSergeant Bluff, IAWoodbury CountyMidAmerican Energy Co584 MW
Greater Des MoinesPlant 7985Oil & gasPleasant Hill, IAPolk CountyMidAmerican Energy Co576 MW
Highland Wind Project (IA)Plant 58883WindPrimghar, IAO'Brien CountyMidAmerican Energy Co502 MW
Orient Wind FarmPlant 61077WindOrient, IAAdair CountyMidAmerican Energy Co501 MW

Methodology

Transparent by design

State totals and fuel mix use finalized EIA-860 2024 generator data. The facility table uses the EIA-860 2025 Early Release and is preliminary. Data-center counts use OpenStreetMap community records and measure mapped coverage, not the full market.

EIA-860 sourceOpenStreetMap